If installing a CT, a Chint Meter is NOT required.
- The CT needs to be just before or just after the customers Main Switch on the live
conductor - Not to be installed on the Non-essential loads
- The arrow on the side of the CT needs to point towards the Grid
- Locate the COMMS plug that plugs into the METER/CT/RS485 port on the inverter
- The Red + wire needs to be terminated on pin 8 + of the comms plug
- The Black – wire needs to be terminated on pin 7 – of the comms plug
- Plug the wired Comms plug into the METER/CT/RS485 port on the inverter